- 2023
-
The total capacity of solid waste anaerobic treatment exceeded 35,000tons/day
-
- 2020
-
The first semi-underground solid waste anaerobic treatment system in China—Xiong’an comprehensive waste treatment project contract was signed
-
- 2019
-
Purac China reorganized to be the headquarter of whole group to fully develop the domestic waste treatment market, and Purac Sweden provided technical support.
-
- 2018
-
Introduced DRANCO dry anaerobic process and HYBACS municipal sewage upgrading process into China
-
- 2017
-
The first whole process EPC project - Suzhou industrial Park restaurant waste and green waste treatment project contract was signed
-
- 2016
-
A number of sludge advanced anaerobic treatment projects were put into operation, such as Beijing Gaobeidian、Xiaohongmen、Qinghe、Huaifang
-
- 2015
-
SDIC&BDG water investment fund acquired Purac Group
-
- 2014
-
PURAC was awarded as the leader of organic waste anaerobic treatment solution in the field of solid waste industry by E20
-
- 2013
-
One Belt and Road project contract was signed-Malaysia Pantai wwtp sludge treatment project
-
- 2012
-
Chongqing Heishizi restaurant waste treatment phase IV project contract was signed, the capacity of whole project reached 1000tons/day
-
- 2010
-
Signed a number of pulp and paper and other industrial wastewater treatment projects
-
- 2009
-
Purac strategically targeted restaurant waste anaerobic treatment market and signed the first project in this field, Chongqing Heishizi restaurant waste treatment phase I project
-
- 2003
-
Established a wholly-owned company, Purac Environmental System (Beijing) Co., Ltd.
-
- 1996
-
The first pulp and paper waste water project contract was signed, with capacity of 23,000tons/day
-
- 1994
-
The first municipal water supply project contract was signed with capacity of 100,000tons/day
-
- 1993
-
Signed Gaobeidian WWTP project and entered into China, set up representative office in Beijing
-
- 1956
-
Purac Group was founded in Sweden